Gemba Report List

No Finding Date HAC Description Status Action
673 2026-07-28 531-BC1 Kebocoran material di Inlet chute Done View
674 2026-07-28 561-RF1 Ada nya kebocoran material dr pipa hot gas Done View
675 2026-07-28 591-BE1 Bearing noise, seal bearing rusak, material bocor Done View
676 2026-07-23 61A-PG1 Cleaning dan penempelan poster Done View
677 2026-07-23 61A - BL1 Cleaning dan penempelan poster Done View
678 2026-07-23 62A-FA1 Cleaning dan penempelan poster Done View
679 2026-07-23 61A-BF1 Cleaning dan penempelan poster Done View
680 2026-07-23 61A - AS2 Cleaning dan penempelan poster Done View
681 2026-07-23 61A - AS1 Cleaning dan penempelan poster Done View
682 2026-07-23 61A-VS1 Cleaning dan penempelan poster Done View
683 2026-07-23 61A-FN1 Cleaning dan penempelan poster Done View
684 2026-07-23 61A-3B1 Cleaning dan penempelan poster Done View
685 2026-07-28 61A-FN1 Casing kotor Done View
686 2026-07-28 62A-VS1 Casing kotor Done View
687 2026-07-28 61A - AS1 Casing kotor Done View
688 2026-07-28 61A-3B1 Lantai kotor Done View
689 2026-07-23 61A-PG1 berdebu Done View
690 2026-07-23 62A-VS1 spilage semen Done View
691 2026-07-23 61A-FN1 spilage semen Done View
692 2026-07-23 61A-3B1 banyak spilage semen Done View
693 2026-07-27 61A - AS2 Cleaning dan tempel poster Done View
694 2026-07-27 61A-FN1 Cleaning dan tempel poster Done View
695 2026-07-27 61A-VS1 Cleaning dan tempel poster Done View
696 2026-07-27 61A-3B1 Cleaning dan tempel poster Done View
697 2026-07-27 61A-3B1 Cleaning dan tempel poster Done View
698 2026-07-27 Pile coal smoldering di pile coal Done View
699 2026-07-27 L21-BC3 Rubber V-ploug head aus Done View
700 2026-07-21 L21-BC3 Inlet chute Utara bolong Done View
701 2026-07-16 361-RM1 Casing feed chute bolong Done View
702 2026-07-13 331- BC1 Manhole Utara baut hilang semua Done View
703 2026-07-27 462-KL1 Inlet Cleaning coating inlet kiln ok Done View
704 2026-07-27 362-MS1 Quick fix cleaning MS material sudah penuh ok Done View
705 2026-07-27 662-BW1 Repainting Box timbel bandul kalibrasi Done View
706 2026-07-27 362-BE1 Quick fix cleaning bottom BE material sudah penuh ok Done View
707 2026-07-27 Area L11-BC1 Quick fix cleaning bawah BC ada smoldering Done View
708 2026-07-07 K91-RE1 QuickFix. Bucket Scrapper rec crack potensi rusak Done View
709 2026-07-22 591-FN06 QuickFix. Draft bottom terlalu over setting Done View
710 2026-07-27 61B-3B1 Gemba 2 Juli 2026. Material spillage dari surge bin Done View
711 2026-07-24 511-FN4 QuickFix. Blade unbalance krn material build up di blade Done View
712 2026-07-24 591-FAA QuickFix. Inlet screen hampir buntu Done View
713 2026-07-24 561-RM1 QuickFix. Stopper roller lepas Done View
714 2026-07-27 K11-ST1 QuickFix. Sensor sensing boom material abnormal Done View
715 2026-07-27 61B-FN1 Gemba 2 Juli 2026. Cleaning material di atas surge bin Done View
716 2026-07-27 61B-3B1 Gemba 2 Juli 2026. Cleaning material di atas casing AS Done View
717 2026-07-08 332-WF2 Quick fix cleaning penempelan outlet chute wf silika Done View
718 2026-07-08 332-BC1 Quick fix evakuasi dan install clamp rubber curtain inlet chute yg lepas dan menggesek belt Done View
719 2026-07-08 362-RM1 Quick fix install shim plate roller 1 yg lepas Done View
720 2026-07-08 362-CH1 Quick fix tambal false air di inlet chute raw mill Done View