Gemba Report List

No Finding Date HAC Description Status Action
2977 2026-06-26 562-RF1 Valve hot gas kotor Done View
2978 2026-06-26 562-RF1 Casing sisi selatan rotary feeder kotor Done View
2979 2026-06-26 562-RF1 Handrail bin reject kotor Done View
2980 2026-06-26 562-RF1 Casing gas chamber kotor Done View
2981 2026-06-26 562-RF1 Casing valve tertimbun debu Done View
2982 2026-06-26 562-RF1 floor Handrail bertumpuk debu Done View
2983 2026-06-26 562-RF1 Handrail kotor Done View
2984 2026-06-26 391-BE1 Cover bottom joint belt mengelupas Done View
2985 2026-06-22 Non Shift Room 2 Merapikan lemari dokumen Done View
2986 2026-06-26 Lab - R. Furnace PQC Cleaning furnace dari debu Done View
2987 2026-06-26 421-BF 1 Shaft puppet valve patah Done View
2988 2026-06-26 562-RM1 terdapat sampah kaleng bekas cat di area Done View
2989 2026-06-20 Lab Fisika Colokan kotor Done View
2990 2026-06-20 Laborat Ruang Alat Ruang alat berantakan Done View
2991 2026-06-20 Lab Fisika Selokan kotor Done View
2992 2026-06-25 Ruang Sample Lab Fisika Banyak sample yang menumpuk Done View
2993 2026-06-25 H-Ruang Oven/Furnace PQC Oven kotor Done View
2994 2026-06-25 H-Ruang Oven/Furnace PQC Oven kotor Done View
2995 2026-06-25 431-EH1 Ujung sling hoist rantas & belum di clamp,kondisi ini unsafe untuk proses lifting Done View
2996 2026-06-25 361-RF1 Casing RF leakage, material menumpuk di sekitar RF Done View
2997 2026-06-25 L61-SX1 Support baseplate SX crack Done View
2998 2026-06-25 361-BE1 Bucket beberapa deform Done View
2999 2026-06-26 PH TQ 2 grond Cleaning ceceran material Done View
3000 2026-06-26 PH TQ 2 grond Cleaning ceceran material Done View
3001 2026-06-26 PH TQ 2 grond Cleaning ceceran material Done View
3002 2026-06-26 PH TQ 2 grond Cleaning ceceran material Done View
3003 2026-06-26 PH TQ 2 grond Cleaning ceceran material Done View
3004 2026-06-26 PH TQ 2 grond Cleaning ceceran material Done View
3005 2026-06-25 L61-RF1 Pintu tangga menuju RF lepas engsel patah. Kondisi ini unsafe karena akses terbatas. Done View
3006 2026-06-26 Pump house plant seal pompa bocor Done View
3007 2026-06-26 L61-FN1 tumpukan daun mengotori bahu jalan Done View
3008 2026-06-26 L61-FN1 area bawah panel kotor Done View
3009 2026-06-26 L61-FN1 lantai kotor Done View
3010 2026-06-26 L61-FN1 ceceran material di sekitar area FN1 Done View
3011 2026-06-26 L61-FN1 ceceran material di area floor Done View
3012 2026-06-25 462-KL1 Inlet Kiln QF) Pintu bungker inlet kiln seal terbuka sehingga unsafe jika ada material yg keluar dari inlet seal Done View
3013 2026-06-10 361-MD1 Cleaning area lantai Done View
3014 2026-06-26 L21-MW2 Bocoran material karena gap overlap pengarah ke blade ada gap 50 mm Done View
3015 2026-06-26 331-BC1 Return roller aus dan berpotensi merusak belt Done View
3016 2026-06-26 X91-BC4 Belt mengelupas karena tersangkut batu di plat skirt Done View
3017 2026-06-26 X91-BC4 Secondary scraper terlalu menekan belt, belt scratch sepanjang permukaan, devcon untuk perbaikan Done View
3018 2026-06-26 331-WF3 Retturn roller tengah kecil stuck, menghambat pergerakan belt Done View
3019 2026-06-26 431-EH1 Ujung wire sling hoist preheater terurai dan tidak terpasang dengan benar Done View
3020 2026-06-26 L01-FT1 Hose tangki solar lepas, sambungan bocor dan tidak aman untuk pengisian Done View
3021 2026-06-26 361-CV1 sensor skewing kotor Done View
3022 2026-06-26 491-BF1 coil solenoid valve bag filter putus Done View
3023 2026-06-26 X91-BC4 Cleaning area platform sekitar BC Done View
3024 2026-06-26 471-RC1 sensor speed swicth roler crusher lepas Done View