No Finding Date HAC Description Status Action
2113 2026-06-10 361-MD1 Cleaning area Done View
2114 2026-06-24 corrective material TQ2 Cleaning tumpahan copper slag Done View
2115 2026-06-24 corrective material TQ2 Cleaning pallet bekas dan tumpahan copper slag Done View
2116 2026-06-10 361-MD1 Cleaning area Done View
2117 2026-06-24 corrective material TQ2 Cleaning tumpahan copper slag Done View
2118 2026-06-24 corrective material TQ2 Cleaning material yang luber Done View
2119 2026-06-22 corrective material TQ1 Cleaning selokan Done View
2120 2026-06-22 corrective material TQ1 Cleaning selokan Done View
2121 2026-06-22 Cleaning ceceran material Cleaning ceceran material Done View
2122 2026-06-22 corrective material TQ1 Kupas material copper slag depan storage Done View
2123 2026-06-25 61C-PG3 Kondisi pipa aerasi bocor Done View
2124 2026-06-29 corrective material TQ1 Cleaning material copper slag Done View
2125 2026-06-25 641-VS01 Bracing hisapan ducting BF ke VS lepas Done View
2126 2026-06-25 61C-VS1 Flexible inlet dan hisapan VS berlubang Done View
2127 2026-06-23 Gudang Copper Slag TQ1 Selokan ditumbuhi rumput dan endapan tanah Done View
2128 2026-06-25 511-FN4 Ducting outlet screen FN banyak coating material Done View
2129 2026-06-26 332 RM1 sampah Done View
2130 2026-06-26 332 RM1 got kotor Done View
2131 2026-06-26 422-SC2 pagar hampir roboh Done View
2132 2026-06-26 422-SC2 oli / grease motor bocor Done View
2133 2026-06-23 Gudang Copper Slag TQ1 Genangan air Done View
2134 2026-06-26 422-SC2 oli / grease motor bocor Done View
2135 2026-06-26 422-SC2 kabel tray utara raw mill 2 menggantung tanpa baricade Done View
2136 2026-06-23 Gudang Copper Slag TQ1 Ceceran material Done View
2137 2026-06-23 Gudang Copper Slag TQ1 Botol berserakan Done View
2138 2026-06-26 422-SC2 Lampu yang tidak dimatikan dan auto di off kan krn OH Done View
2139 2026-06-29 291-ST1 Komunikasi ke DCS belum normal Done View
2140 2026-06-26 532-WF1 Panel vsd kotor Done View
2141 2026-06-29 X91-BC 4 Material Spillage di bawah X91-BC4 Done View
2142 2026-06-29 311 - BC1 Material spillage di head pulley 311-BC1 Done View
2143 2026-06-29 661-BA1 Mesin Bag Aplicator rusak akibat motor belum sinkron Done View
2144 2026-06-29 291-ST1 Setting komunikasi Wireless 291-ST1 belum sesuai, sehingga muncul error Done View
2145 2026-06-25 512-PN3 Casing outlet PN berlubang Done View
2146 2026-06-26 311-BC1 Tumpahan material dari sisi kiri/selatan head BC bekas material blocking Done View
2147 2026-06-26 311-BC1 Tumpahan material sisa blocking dari sisi kanan casing BC Done View
2148 2026-06-26 311-BC1 Tumpahan material dari check hole head BC Done View
2149 2026-06-25 l01- FT1 Ceceran RCO depan pump room kiln, cleaning(quick fiks) Done View
2150 2026-06-26 X91-BC4 Spillage material under BC Done View
2151 2026-06-22 l01- FT1 Ceceran RCO depan pump room kiln, cleaning(quick fiks) Done View
2152 2026-06-26 K91-BC4 Spillage material under BC Done View
2153 2026-06-22 L01-FP1 Ceceran RCO depan pump room kiln, cleaning(quick fiks) Done View
2154 2026-06-22 L01-FP1&2 Ceceran RCO depan pump room kiln, cleaning(quick fiks) Done View
2155 2026-06-25 562-RF1 Casing bawah checkhole RF ada yg berlubang Done View
2156 2026-06-29 491 - AC 1 Rel ngangkan perlu d tek well lagi Not Yet View
2157 2026-06-23 l01- FT1 Pengosongan tangki RCO, cleaning(quick fiks) Done View
2158 2026-06-25 532-EH2 Panel lis kotor Done View
2159 2026-06-19 432-BE1 Bearing bottom grese menghitam Done View
2160 2026-06-23 L01-FP1 Pengosongan tangki RCO. Cleaning(quick fiks) Done View